Completed fictional example: Handle a mid-project scope change before work continues
All people, identifiers, amounts, outcomes, and internal evidence are fictional. This example demonstrates how to complete the record; it is not a client case or an account test.
Project / original accepted proposal and version
WEB-014 / proposal v2, demo acceptance A-02
Change ID / requester / date
CH-02 / Jamie / October 2, 2026
Request and difference from the baseline
Add a Contact page and form; original scope was one home page
Classification: correction / clarification / new scope
New scope
Deliverable impact and retained work
Contact page added; original home page retained
Price basis / tax treatment under the agreement
Illustrative fixed $600 addition; same tax treatment as the original proposal
Timing and required inputs
October 16 if copy arrives by October 12
Options and client reply
Keep the original scope and date, or add the page with the addition and delay; model wording in the article
Decision maker / answer / evidence / date
Jamie, designated decision maker in the demo agreement, explicitly accepts CH-02 October 5; demo reply A-03
Outcome and plan update / owner
Accepted; Casey updates tasks and timing referencing CH-02; original proposal retained
Two alternative outcomes for the same model
Declined: Jamie chooses the original scope and date on October 5. Mark CH-02 declined; Casey does not start the added work.
Conditional: “Add the page but keep the original deadline.” CH-02 remains open; Casey checks capacity by October 6 and submits a revised option for a decision. Do not infer agreement to the addition or date. These are alternative scenarios, not concurrent decisions.